11 Logan Street, Glenroy - 公共项目现场
-
27th 十月 2025, Weekly Bulletin Monday 27th of October (Glenroy)
Hi all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
- GF slab prep completed
- Steel & Blocks delivered Wednesday
- GF slab pour scheduled Thursday
- Surveyor Set out GF & blocks starting on Friday
- Column steel commences on Friday
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know
Site is closed Monday 3rd & 4th of November due to Melbourne cup -
20th 十月 2025, Weekly Bulletin Monday 20th of October
Hi all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
Monday through to Friday
- We have GF slab prep
- Steel delivery & Pods
- Steel install
- Electrical conduits installed
- Slab base Inspection
- Surveyor set out
- Termite spray & collars
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know -
06th 十月 2025, Monday 6th of October (Weekly Bulletin Glenroy)
Hi all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
- Monday we have the plumber continuing with his in ground services this will continue throughout the week & be completed on Friday
- Tuesday & Thursday the electrician will come in and complete all electrical in grounds and conduit work.
Thanks Jake (Glenroy)
Please note - School holidays are finished so be mindful of deliveries around school pick up & drop off times
当前现场天气
不可用
时区 - 澳大利亚东部标准时间
预测 - 星期五、7 十一月
不可用
明天 - 星期六, 8 十一月
不可用