11 Logan Street, Glenroy - Cantiere del progetto pubblico
-
06th marzo 2026, Weekly bulletin (Glenroy)
Hi All
Please be advised Site is closed on Monday the 9th of March due to the public holiday.
Stay safe & enjoy
Thanks Jake (Glenroy) -
17th febbraio 2026, Weekly bulletin Tuesday 17th of February (Glenroy)
Morning all this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- Plumbing rough in commenced
- GF & FF Wall wrap
- Pergola Beam install
- FF roof install (Wednesday)
- Carpentry rough in
Thanks Jake
Any issues please let me know -
09th febbraio 2026, Weekly bulletin Monday 9th of February (Glenroy)
Morning all this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- GF wall framing completed
- FF walls and roof completed
- Strip formwork from stairs x2
- Thursday we have Pergola Materials delivery front entry will be a no go zone for the duration of this delivery.
Thanks Jake
Any issues please let me know
Meteo attuale del cantiere
Non disponibile
Fuso orario - Ora standard dell’Australia orientale
Previsioni - martedì, 10 marzo
Non disponibile
Domani - mercoledì, 11 marzo
Non disponibile
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.