  • 22nd luglio 2026, Weekly Bulletin Wednesday 22nd July (Glenroy)

    Hi All
    As we have had the main building cleaned please DO NOT walk inside with muddy boots/footwear.
    You will be made to clean your own mess.

    Thanks Jake

  • 14th luglio 2026, Weekly bulletin Tuesday 14 July

    Hi All
    Friday we will be pouring the Crossover and footpath access will be limited to site but still available.
    Please be wary of trucks coming and going, traffic management will be in place for the pour.

    Thanks Jake

  • 13th luglio 2026, Weekly bulletin 11 Logan Street Glenroy

    Hi All
    Please be advised not to leave any tools or Materials on the footpath/nature strip as Council has advised us they will implement fines.
    Please store all materials behind the gate.

    Any issues Let me know
    Thanks Jake

Previsioni meteo del cantiere
Meteo attuale del cantiere

Non disponibile


Osservazione proveniente da - Non disponibile
Fuso orario - Ora standard dell’Australia orientale
Previsioni - sabato, 15 agosto

Non disponibile


Fuso orario - Ora standard dell’Australia orientale
Domani - domenica, 16 agosto

Non disponibile


Documenti importanti per il cantiere
Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Nuovo sul cantiere?

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione