06th mars 2026, Weekly bulletin (Glenroy)
Hi All
Please be advised Site is closed on Monday the 9th of March due to the public holiday.
Stay safe & enjoy
Thanks Jake (Glenroy) -
17th februari 2026, Weekly bulletin Tuesday 17th of February (Glenroy)
Morning all this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- Plumbing rough in commenced
- GF & FF Wall wrap
- Pergola Beam install
- FF roof install (Wednesday)
- Carpentry rough in
Thanks Jake
Any issues please let me know -
09th februari 2026, Weekly bulletin Monday 9th of February (Glenroy)
Morning all this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- GF wall framing completed
- FF walls and roof completed
- Strip formwork from stairs x2
- Thursday we have Pergola Materials delivery front entry will be a no go zone for the duration of this delivery.
Thanks Jake
Any issues please let me know
Nuvarande väder på platsen
Otillgänglig
Tidszon - östaustralisk normaltid
Prognos - tisdag, 10 mars
Otillgänglig
Imorgon - onsdag, 11 mars
Otillgänglig
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.