06th Ekim 2025, Monday 6th of October (Weekly Bulletin Glenroy)
Hi all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
- Monday we have the plumber continuing with his in ground services this will continue throughout the week & be completed on Friday
- Tuesday & Thursday the electrician will come in and complete all electrical in grounds and conduit work.
Thanks Jake (Glenroy)
Please note - School holidays are finished so be mindful of deliveries around school pick up & drop off times -
22nd Eylül 2025, Weekly Bulletin 22nd of September (Glenroy)
This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday
- Monday we have engineer scheduled for a site visit to inspect bored piers
- Tuesday we have Rockend starting to core drill all bored piers as required (Will potentially continue all week)
- Thursday concrete TBC (depending on core drilling works
Thanks Jake (Glenroy)
Please note Friday is a public holiday site will be closed -
20th Nisan 2021, Heavy Rain & Strong Winds
Heavy rain and strong winds predicted across Melbourne this afternoon. Please ensure sites are safe with building materials tied down, fences secure and pumps are functioning and turned on.
Geçerli Saha Hava Durumu
Kullanılamaz
Zaman Dilimi - Doğu Avustralya Standart Saati
Tahmin - Pazartesi, 13 Ekim
Kullanılamaz
Yarın - Salı, 14 Ekim
Kullanılamaz
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.