11 Logan Street, Glenroy - Veřejná stránka projektu
-
10th dubna 2026, Weekly Bulletin 10th April 2026
Hi All
Next week at Glenroy:
We have a big milestone we have Main water tap in on Monday 13th April which will result in the road being blocked off.
Please park away from the front entrance, all deliveries will have to be rescheduled for Tuesday onwards.
Thanks Jake
Enjoy your weekend -
30th března 2026, Weekly bulletin Monday 30th March (Glenroy)
Good morning this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday
Site closed Friday 3rd April
Site closed Monday 6th of April
- GF & FF cladding all week
- GF Pergola install all week
- GF external brickwork all week
- Sash window install Tuesday & window install
Thanks Jake
Any issues please let me know -
23rd března 2026, Weekly bulletin Monday 23rd March (Glenroy)
Good morning this week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- GF landscape & FF shade sail post install
- Plaster battens & Cladding install GF & FF throughout the week
- GF external Bricks starting Monday and continuing for the next week
- FF & GF pergola re commencing Tuesday throughout the week
- Window installation completed on Thursday
Thanks Jake
Any issues please let me know
Aktuální počasí na pracovišti
Nedostupné
Časové pásmo - východoaustralský standardní čas
Předpověď – středa, 29 dubna
Nedostupné
Zítra - čtvrtek, 30 dubna
Nedostupné
Znáte požadavky na OOPP pro toto pracoviště?
Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.
Po příjezdu na místo můžete začít pracovat dříve.
Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.
Znáte požadavky na OOPP pro toto pracoviště?
Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.
Po příjezdu na místo můžete začít pracovat dříve.
Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.