11 Logan Street, Glenroy - Site proiect public
-
06th octombrie 2025, Monday 6th of October (Weekly Bulletin Glenroy)
Hi all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
- Monday we have the plumber continuing with his in ground services this will continue throughout the week & be completed on Friday
- Tuesday & Thursday the electrician will come in and complete all electrical in grounds and conduit work.
Thanks Jake (Glenroy)
Please note - School holidays are finished so be mindful of deliveries around school pick up & drop off times -
22nd septembrie 2025, Weekly Bulletin 22nd of September (Glenroy)
This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday
- Monday we have engineer scheduled for a site visit to inspect bored piers
- Tuesday we have Rockend starting to core drill all bored piers as required (Will potentially continue all week)
- Thursday concrete TBC (depending on core drilling works
Thanks Jake (Glenroy)
Please note Friday is a public holiday site will be closed -
20th aprilie 2021, Heavy Rain & Strong Winds
Heavy rain and strong winds predicted across Melbourne this afternoon. Please ensure sites are safe with building materials tied down, fences secure and pumps are functioning and turned on.
Condiții meteo curente la șantier
Indisponibil
Fus orar - Ora standard a Australiei Orientale
Prognoză - luni, 13 octombrie
Indisponibil
Mâine - marți, 14 octombrie
Indisponibil
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.