  • 05th stycznia 2026, Welcome back to wheelers hill

    Weekly bulletin.
    Welcome back to Wheelers hill

    Monday 05/01/2026
    ICC Return to site and begin basement SOG prep
     
    Tuesday 06/01/2026
    ICC continue basement SOG prep
     
    Wednesday 07/01/2026
    ICC Poly and Mesh Basement SOG
     
    Thursday 08/01/2026
    ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
    Preslab Inspection in afternoon
     
    Friday 09/01/2026
    ICC Pour Basement Slab
     
    Saturday 10/01/2026
    ICC Sawcut Slab
    ICC Install Starter Bars for Columns
     
    Monday 12/01/2026
    Adbri Block Delivery
    ICC Cages and Formwork for Columns
    Masonry Masters Install Blocks
     
    Tuesday 13/01/2026
    ICC Cages and Formwork for Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Wednesday 14/01/2026
    ICC Close Up Formwork for Columns
    Column Inspection
    ICC Pour Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Thursday 15/01/2026
    Donmar Corefill Blocks
    ICC Ramp Prep
    Ramp Inspection
     
    Friday 16/01/2026
    ICC Pour Ramp

  • 15th grudnia 2025, Weekly bulletin Monday 15th of December (Glenroy)

    Good morning all This week & next week at Glenroy:

    Monday, Tuesday, Wednesday, Thursday & Friday
    Monday - 22nd December

    15/12/25 - 18/12/25
    - Clean FF deck
    - Crush rock entry
    - Complete FF formwork
    TUESDAY
    - Pour FF deck
    Hi Vis & Hard hats MUST BE WORN
    - Traffic control will be in place
    Wednesday
    - PTX stress 25%
    - Strip formwork
    Thursday
    - FF set out
    - Strip formwork
    Site is closed Friday the 19th

    Monday 22nd Dec - Site open for PT final stress

    Thanks Jake
    Merry Christmas & A Happy New Year
    Site will reopen for 2026 on Monday 12th of January

  • 08th grudnia 2025, Weekly Bulletin Monday 8th of December (Glenroy)

    DonmarConst - Good morning all This week & next week at Glenroy:

    Monday, Tuesday, Wednesday, Thursday & Friday

    8/12/25 - 12/12/25
    - Hobs + steps formed up
    - Bottom steel install
    - PT install on Tuesday
    - Top steel install
    - PT inspection scheduled for Friday arvo

    15-12-25 - 22-12-25
    Tuesday FF slab Pour
    Wednesday PT first stress and strip stop ends
    Surveyor set out FF
    Friday - SITE CLOSED
    Monday 22nd site open for PT final stress

    Thanks Jake (Glenroy)
    Please note - Deliveries must be worked around school pick up & drop off times
    If there is any issues please let me know
    Merry Christmas & A Happy New Year

Prognoza pogody placu budowy
Aktualna pogoda w lokalizacji

Niedostępne


Źródło spostrzeżenia - Niedostępne
Strefa czasowa - czas wschodnioaustralijski standardowy
Prognoza - środa, 21 stycznia

Niedostępne


Strefa czasowa - czas wschodnioaustralijski standardowy
Jutro - czwartek, 22 stycznia

Niedostępne


Ważne dokumenty lokalizacji
Nowy użytkownik w lokalizacji?

Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?

Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.

Pokaż wymagania SOI na placu budowy

Rozpocznij pracę szybciej po przybyciu do lokalizacji

Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.

Rozpocznij rejestrację

Nowy użytkownik w lokalizacji?

Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?

Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.

Pokaż wymagania SOI na placu budowy

Nowy użytkownik w lokalizacji?

Rozpocznij pracę szybciej po przybyciu do lokalizacji

Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.

Rozpocznij rejestrację

;