ICC Return to site and begin basement SOG prep
Tuesday 06/01/2026
ICC continue basement SOG prep
Wednesday 07/01/2026
ICC Poly and Mesh Basement SOG
Thursday 08/01/2026
ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
Preslab Inspection in afternoon
Friday 09/01/2026
ICC Pour Basement Slab
Saturday 10/01/2026
ICC Sawcut Slab
ICC Install Starter Bars for Columns
Monday 12/01/2026
Adbri Block Delivery
ICC Cages and Formwork for Columns
Masonry Masters Install Blocks
Tuesday 13/01/2026
ICC Cages and Formwork for Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Wednesday 14/01/2026
ICC Close Up Formwork for Columns
Column Inspection
ICC Pour Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Thursday 15/01/2026
Donmar Corefill Blocks
ICC Ramp Prep
Ramp Inspection
Friday 16/01/2026
ICC Pour Ramp
-
15th Dezember 2025, Weekly bulletin Monday 15th of December (Glenroy)
Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
Monday - 22nd December
15/12/25 - 18/12/25
- Clean FF deck
- Crush rock entry
- Complete FF formwork
TUESDAY
- Pour FF deck
Hi Vis & Hard hats MUST BE WORN
- Traffic control will be in place
Wednesday
- PTX stress 25%
- Strip formwork
Thursday
- FF set out
- Strip formwork
Site is closed Friday the 19th
Monday 22nd Dec - Site open for PT final stress
Thanks Jake
Merry Christmas & A Happy New Year
Site will reopen for 2026 on Monday 12th of January -
08th Dezember 2025, Weekly Bulletin Monday 8th of December (Glenroy)
DonmarConst - Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
8/12/25 - 12/12/25
- Hobs + steps formed up
- Bottom steel install
- PT install on Tuesday
- Top steel install
- PT inspection scheduled for Friday arvo
15-12-25 - 22-12-25
Tuesday FF slab Pour
Wednesday PT first stress and strip stop ends
Surveyor set out FF
Friday - SITE CLOSED
Monday 22nd site open for PT final stress
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know
Merry Christmas & A Happy New Year
Aktuelles Wetter am Standort
Nicht verfügbar
Zeitzone - Ostaustralische Normalzeit
Vorhersage - Mittwoch, 21 Januar
Nicht verfügbar
Morgen - Donnerstag, 22 Januar
Nicht verfügbar
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.