11 Logan Street, Glenroy
Boletines recientes
  • 05th enero 2026, Welcome back to wheelers hill

    Weekly bulletin.
    Welcome back to Wheelers hill

    Monday 05/01/2026
    ICC Return to site and begin basement SOG prep
     
    Tuesday 06/01/2026
    ICC continue basement SOG prep
     
    Wednesday 07/01/2026
    ICC Poly and Mesh Basement SOG
     
    Thursday 08/01/2026
    ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
    Preslab Inspection in afternoon
     
    Friday 09/01/2026
    ICC Pour Basement Slab
     
    Saturday 10/01/2026
    ICC Sawcut Slab
    ICC Install Starter Bars for Columns
     
    Monday 12/01/2026
    Adbri Block Delivery
    ICC Cages and Formwork for Columns
    Masonry Masters Install Blocks
     
    Tuesday 13/01/2026
    ICC Cages and Formwork for Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Wednesday 14/01/2026
    ICC Close Up Formwork for Columns
    Column Inspection
    ICC Pour Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Thursday 15/01/2026
    Donmar Corefill Blocks
    ICC Ramp Prep
    Ramp Inspection
     
    Friday 16/01/2026
    ICC Pour Ramp

  • 15th diciembre 2025, Weekly bulletin Monday 15th of December (Glenroy)

    Good morning all This week & next week at Glenroy:

    Monday, Tuesday, Wednesday, Thursday & Friday
    Monday - 22nd December

    15/12/25 - 18/12/25
    - Clean FF deck
    - Crush rock entry
    - Complete FF formwork
    TUESDAY
    - Pour FF deck
    Hi Vis & Hard hats MUST BE WORN
    - Traffic control will be in place
    Wednesday
    - PTX stress 25%
    - Strip formwork
    Thursday
    - FF set out
    - Strip formwork
    Site is closed Friday the 19th

    Monday 22nd Dec - Site open for PT final stress

    Thanks Jake
    Merry Christmas & A Happy New Year
    Site will reopen for 2026 on Monday 12th of January

  • 08th diciembre 2025, Weekly Bulletin Monday 8th of December (Glenroy)

    DonmarConst - Good morning all This week & next week at Glenroy:

    Monday, Tuesday, Wednesday, Thursday & Friday

    8/12/25 - 12/12/25
    - Hobs + steps formed up
    - Bottom steel install
    - PT install on Tuesday
    - Top steel install
    - PT inspection scheduled for Friday arvo

    15-12-25 - 22-12-25
    Tuesday FF slab Pour
    Wednesday PT first stress and strip stop ends
    Surveyor set out FF
    Friday - SITE CLOSED
    Monday 22nd site open for PT final stress

    Thanks Jake (Glenroy)
    Please note - Deliveries must be worked around school pick up & drop off times
    If there is any issues please let me know
    Merry Christmas & A Happy New Year

Pronóstico del tiempo del emplazamiento
Tiempo actual del emplazamiento

No disponible


Observación procedente de - No disponible
Huso horario - hora estándar de Australia oriental
Pronóstico - miércoles, 21 enero

No disponible


Huso horario - hora estándar de Australia oriental
Mañana - jueves, 22 enero

No disponible


Documentos importantes del emplazamiento
¿Es nuevo en el emplazamiento?

¿Conoce los requisitos de EPI para este emplazamiento?

Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.

Visualización de los requisitos del EPI de la obra

Empiece a trabajar antes al llegar "in situ".

Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.

Iniciar el registro

¿Es nuevo en el emplazamiento?

¿Conoce los requisitos de EPI para este emplazamiento?

Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.

Visualización de los requisitos del EPI de la obra

¿Es nuevo en el emplazamiento?

Empiece a trabajar antes al llegar "in situ".

Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.

Iniciar el registro

;