11 Logan Street, Glenroy - Sitio del proyecto público
-
05th enero 2026, Welcome back to wheelers hill
Weekly bulletin.
Welcome back to Wheelers hill
Monday 05/01/2026
ICC Return to site and begin basement SOG prep
Tuesday 06/01/2026
ICC continue basement SOG prep
Wednesday 07/01/2026
ICC Poly and Mesh Basement SOG
Thursday 08/01/2026
ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
Preslab Inspection in afternoon
Friday 09/01/2026
ICC Pour Basement Slab
Saturday 10/01/2026
ICC Sawcut Slab
ICC Install Starter Bars for Columns
Monday 12/01/2026
Adbri Block Delivery
ICC Cages and Formwork for Columns
Masonry Masters Install Blocks
Tuesday 13/01/2026
ICC Cages and Formwork for Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Wednesday 14/01/2026
ICC Close Up Formwork for Columns
Column Inspection
ICC Pour Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Thursday 15/01/2026
Donmar Corefill Blocks
ICC Ramp Prep
Ramp Inspection
Friday 16/01/2026
ICC Pour Ramp
-
15th diciembre 2025, Weekly bulletin Monday 15th of December (Glenroy)
Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
Monday - 22nd December
15/12/25 - 18/12/25
- Clean FF deck
- Crush rock entry
- Complete FF formwork
TUESDAY
- Pour FF deck
Hi Vis & Hard hats MUST BE WORN
- Traffic control will be in place
Wednesday
- PTX stress 25%
- Strip formwork
Thursday
- FF set out
- Strip formwork
Site is closed Friday the 19th
Monday 22nd Dec - Site open for PT final stress
Thanks Jake
Merry Christmas & A Happy New Year
Site will reopen for 2026 on Monday 12th of January -
08th diciembre 2025, Weekly Bulletin Monday 8th of December (Glenroy)
DonmarConst - Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
8/12/25 - 12/12/25
- Hobs + steps formed up
- Bottom steel install
- PT install on Tuesday
- Top steel install
- PT inspection scheduled for Friday arvo
15-12-25 - 22-12-25
Tuesday FF slab Pour
Wednesday PT first stress and strip stop ends
Surveyor set out FF
Friday - SITE CLOSED
Monday 22nd site open for PT final stress
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know
Merry Christmas & A Happy New Year
Tiempo actual del emplazamiento
No disponible
Huso horario - hora estándar de Australia oriental
Pronóstico - miércoles, 21 enero
No disponible
Mañana - jueves, 22 enero
No disponible
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.