11 Logan Street, Glenroy - 公共プロジェクト現場
-
24th 11月 2025, Weekly bulletin Monday 24th of November
Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
24/11/25 - 28/11/25
- Pour Carpark slab
- Strip Carpark slab
- Apex formwork will commence the FF upper deck and continue throughout the week
- Temporary scaffolding stairs will be installed later in the week for access
1/12/25 - 5/12/25
- Apex will continue with FF upper deck and stair form
- Surveyor will set out FF deck
- Fire collars & Penos will be installed
- Bottom Steel install
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know -
17th 11月 2025, Weekly Bulletin Monday 17th Of November
Good morning all This week & next week at Glenroy:
Monday, Tuesday, Wednesday, Thursday & Friday
- Strip all formwork for columns on Monday & Tuesday
- Plumbing in grounds Carpark slab Monday & Tuesday
- Carpark Prep will start Wednesday and we will pour Carpark slab on Friday
24/11/25 - 28/11/25
- Strip Carpark slab
- Apex formwork will commence the FF upper deck and continue throughout the week
- Temporary scaffolding stairs will be installed later in the week for access
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know -
10th 11月 2025, Monday 10th of November (Glenroy)
Good morning all This week at Glenroy :
Monday, Tuesday, Wednesday, Thursday & Friday
- Columns steel complete
- Shutters install for columns GF throughout the week
- Blockwork complete GF on Tuesday
- Pour GF columns on Friday
- Corefill GF block work Friday
Thanks Jake (Glenroy)
Please note - Deliveries must be worked around school pick up & drop off times
If there is any issues please let me know
現在の現場の天気
利用できません
タイムゾーン - オーストラリア東部標準時
予測 - 金曜日, 28 11月
利用できません
明日 - 土曜日, 29 11月
利用できません