126A Hayston Boulevard, Epping
近期公告
  • 10th 六月 2025, Weekly bulletin 10th June (Epping)

    Hi all
    I hope everyone enjoyed the long weekend.

    This week at Epping :

    Tuesday, Wednesday, Thursday, Friday
    - FF & GF landscape will be continued throughout the week
    - Balustrade Glass Install will commence Thursday
    - Lift install is scheduled for the whole week
    - Stainless steel kitchen install is scheduled for Wednesday
    - Carpark Linemarking is scheduled for Wednesday
    - Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
    - Carpentry fit off will be completed Wednesday
    - Power is TBC
    - Pre final inspection is scheduled 10am
    All outstanding works to be completed prior too



    Thanks Jake (Epping)
    Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion.

  • 02nd 六月 2025, Weekly bulletin Monday 2nd of June

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Builders clean is scheduled for Monday & Tuesday
    - Plumbing fit off will be completed by Wednesday
    - Balustrade Glass Install will commence Monday
    - Lift install is scheduled for the whole week
    - Toilet partitions are scheduled for Tuesday
    - Caulking will continue Thursday onwards
    - Friday power will be connected to site

    Site is closed Monday 9th of June Due to a public holiday.


    Thanks Jake (Epping)
    Please note - All subcontractors are to clean there own mess as the internal clean will be completed

  • 26th 五月 2025, Weekly bulletin Epping 26th of May

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Mechanical fit off will start Monday & be completed by Friday
    - Plumbing fit off will be completed by Friday
    - Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
    - Lift delivery is scheduled for the 29th of May
    - Site shed & office will be removed on the 30th of May (AM)

    Thanks Jake (Epping)
    Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.

现场天气预报
当前现场天气

天气不可用


观测信息来自 - Bureau of Meteorology
观测位置 - Bundoora、VICTORIA
时区 - 澳大利亚东部标准时间
预测 - 星期五、27 六月

Partly cloudy.
最低: 3C 最大: 15C
可能有雨。: 10%


预测信息来自 - Bureau of Meteorology
预测位置 - Watsonia、VICTORIA
时区 - 澳大利亚东部标准时间
明天 - 星期六, 28 六月

Partly cloudy.
最低: 4C 最大: 15C
可能有雨。: 30%
预计降雨: 0 至 1mm


重要现场文件
刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

刚到这个现场吗?

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册