126A Hayston Boulevard, Epping
हाल के बुलेटिन
  • 10th जून 2025, Weekly bulletin 10th June (Epping)

    Hi all
    I hope everyone enjoyed the long weekend.

    This week at Epping :

    Tuesday, Wednesday, Thursday, Friday
    - FF & GF landscape will be continued throughout the week
    - Balustrade Glass Install will commence Thursday
    - Lift install is scheduled for the whole week
    - Stainless steel kitchen install is scheduled for Wednesday
    - Carpark Linemarking is scheduled for Wednesday
    - Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
    - Carpentry fit off will be completed Wednesday
    - Power is TBC
    - Pre final inspection is scheduled 10am
    All outstanding works to be completed prior too



    Thanks Jake (Epping)
    Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion.

  • 02nd जून 2025, Weekly bulletin Monday 2nd of June

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Builders clean is scheduled for Monday & Tuesday
    - Plumbing fit off will be completed by Wednesday
    - Balustrade Glass Install will commence Monday
    - Lift install is scheduled for the whole week
    - Toilet partitions are scheduled for Tuesday
    - Caulking will continue Thursday onwards
    - Friday power will be connected to site

    Site is closed Monday 9th of June Due to a public holiday.


    Thanks Jake (Epping)
    Please note - All subcontractors are to clean there own mess as the internal clean will be completed

  • 26th मई 2025, Weekly bulletin Epping 26th of May

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Mechanical fit off will start Monday & be completed by Friday
    - Plumbing fit off will be completed by Friday
    - Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
    - Lift delivery is scheduled for the 29th of May
    - Site shed & office will be removed on the 30th of May (AM)

    Thanks Jake (Epping)
    Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.

साइट पर मौसम का पूर्वानुमान
साइट का मौजूदा मौसम

मौसम उपलब्ध नहीं है


ऑब्जरवेशन- Bureau of Meteorology से लिया गया है
ऑब्जरवेशन की लोकेशन- Bundoora, VICTORIA
समय क्षेत्र - ऑस्‍ट्रेलियाई पूर्वी मानक समय
पूर्वानुमान - शुक्रवार, 27 जून

Partly cloudy.
न्यूनतम: 3C अधिकतम: 15C
बारिश की संभावना: 10%


- Bureau of Meteorology से प्राप्त पूर्वानुमान
पूर्वानुमान वाली लोकेशन - Watsonia, VICTORIA
समय क्षेत्र - ऑस्‍ट्रेलियाई पूर्वी मानक समय
कल - शनिवार, 28 जून

Partly cloudy.
न्यूनतम: 4C अधिकतम: 15C
बारिश की संभावना: 30%
अपेक्षित बारिश: 0 से 1mm


महत्वपूर्ण साइट दस्तावेज़
क्या आप साइट पर नए हैं?

क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?

सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।

साइट PPE की आवश्यकताओं को देखें

जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।

अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।

रजिस्ट्रेशन शुरू करें

क्या आप साइट पर नए हैं?

क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?

सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।

साइट PPE की आवश्यकताओं को देखें

क्या आप साइट पर नए हैं?

जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।

अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।

रजिस्ट्रेशन शुरू करें