126A Hayston Boulevard, Epping
最近のニュースレター
  • 10th 6月 2025, Weekly bulletin 10th June (Epping)

    Hi all
    I hope everyone enjoyed the long weekend.

    This week at Epping :

    Tuesday, Wednesday, Thursday, Friday
    - FF & GF landscape will be continued throughout the week
    - Balustrade Glass Install will commence Thursday
    - Lift install is scheduled for the whole week
    - Stainless steel kitchen install is scheduled for Wednesday
    - Carpark Linemarking is scheduled for Wednesday
    - Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
    - Carpentry fit off will be completed Wednesday
    - Power is TBC
    - Pre final inspection is scheduled 10am
    All outstanding works to be completed prior too



    Thanks Jake (Epping)
    Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion.

  • 02nd 6月 2025, Weekly bulletin Monday 2nd of June

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Builders clean is scheduled for Monday & Tuesday
    - Plumbing fit off will be completed by Wednesday
    - Balustrade Glass Install will commence Monday
    - Lift install is scheduled for the whole week
    - Toilet partitions are scheduled for Tuesday
    - Caulking will continue Thursday onwards
    - Friday power will be connected to site

    Site is closed Monday 9th of June Due to a public holiday.


    Thanks Jake (Epping)
    Please note - All subcontractors are to clean there own mess as the internal clean will be completed

  • 26th 5月 2025, Weekly bulletin Epping 26th of May

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Mechanical fit off will start Monday & be completed by Friday
    - Plumbing fit off will be completed by Friday
    - Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
    - Lift delivery is scheduled for the 29th of May
    - Site shed & office will be removed on the 30th of May (AM)

    Thanks Jake (Epping)
    Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.

現場天気予報
現在の現場の天気

天気情報は利用できません


観察元 - Bureau of Meteorology
観察場所 - Bundoora, VICTORIA
タイムゾーン - オーストラリア東部標準時
予測 - 金曜日, 27 6月

Partly cloudy.
: 3C マックス: 15C
降雨の可能性: 10%パーセント


予測の出典 - Bureau of Meteorology
予測場所 - Watsonia, VICTORIA
タイムゾーン - オーストラリア東部標準時
明日 - 土曜日, 28 6月

Partly cloudy.
: 4C マックス: 15C
降雨の可能性: 30%パーセント
予想降雨量: 0 に 1mm


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始