126A Hayston Boulevard, Epping
Bollettini recenti
  • 10th giugno 2025, Weekly bulletin 10th June (Epping)

    Hi all
    I hope everyone enjoyed the long weekend.

    This week at Epping :

    Tuesday, Wednesday, Thursday, Friday
    - FF & GF landscape will be continued throughout the week
    - Balustrade Glass Install will commence Thursday
    - Lift install is scheduled for the whole week
    - Stainless steel kitchen install is scheduled for Wednesday
    - Carpark Linemarking is scheduled for Wednesday
    - Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
    - Carpentry fit off will be completed Wednesday
    - Power is TBC
    - Pre final inspection is scheduled 10am
    All outstanding works to be completed prior too



    Thanks Jake (Epping)
    Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion.

  • 02nd giugno 2025, Weekly bulletin Monday 2nd of June

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Builders clean is scheduled for Monday & Tuesday
    - Plumbing fit off will be completed by Wednesday
    - Balustrade Glass Install will commence Monday
    - Lift install is scheduled for the whole week
    - Toilet partitions are scheduled for Tuesday
    - Caulking will continue Thursday onwards
    - Friday power will be connected to site

    Site is closed Monday 9th of June Due to a public holiday.


    Thanks Jake (Epping)
    Please note - All subcontractors are to clean there own mess as the internal clean will be completed

  • 26th maggio 2025, Weekly bulletin Epping 26th of May

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Mechanical fit off will start Monday & be completed by Friday
    - Plumbing fit off will be completed by Friday
    - Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
    - Lift delivery is scheduled for the 29th of May
    - Site shed & office will be removed on the 30th of May (AM)

    Thanks Jake (Epping)
    Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.

Previsioni meteo del cantiere
Meteo attuale del cantiere

Meteo non disponibile


Osservazione proveniente da - Bureau of Meteorology
Luogo di osservazione - Bundoora, VICTORIA
Fuso orario - Ora standard dell’Australia orientale
Previsioni - venerdì, 27 giugno

Partly cloudy.
Min: 3C Max: 15C
Possibilità di pioggia: 10%


Previsioni provenienti da - Bureau of Meteorology
Luogo previsioni - Watsonia, VICTORIA
Fuso orario - Ora standard dell’Australia orientale
Domani - sabato, 28 giugno

Partly cloudy.
Min: 4C Max: 15C
Possibilità di pioggia: 30%
Precipitazioni previste: 0 a 1mm


Documenti importanti per il cantiere
Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Nuovo sul cantiere?

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione