126A Hayston Boulevard, Epping
Son Bültenler
  • 05th Mayıs 2025, Weekly bulletin Monday 5th of May (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will start Monday & continue throughout the week.
    - Tiling will commence on Monday for the GF + FF and continue throughout the week.
    - FF landscape will be Monday - Friday
    - Mechanical fit off will continue throughout the week.
    - Plumbing fit off will continue throughout the week

    Thanks Jake (Epping)
    Please note - Walls GF & FF have final coat of paint completed so please be careful.

  • 14th Nisan 2025, Weekly bulletin Monday 14th of April (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday
    - Skirting install GF & FF
    - Scaffolding will be removed in the stairs
    - Vinyl Installation will continue for the week GF & FF
    - External caulking GF & FF will be completed on Monday
    - GF & FF bathrooms will continue tiling on Thursday
    - External Fence work will commence on Tuesday and continue throughout the week
    - Electrical fit off will commence today and continue throughout the week
    - Joinery install will commence today and be completed on Tuesday
    - Brick wash will be commence on Wednesday


    Thanks Jake (Epping)
    Please note - Walls GF & FF will have final coat of paint completed this week if you do damage
    Please let me know (Honesty is the best policy)

    SITE WILL BE CLOSED ON THE 18th of April & re-open ON THE 28th of April.
    Any issues contact me directly
    Jake
    0437464435

  • 07th Nisan 2025, Weekly Bulletin Monday 7th of April (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday & Friday
    - External cladding will continue throughout the week.
    - Plaster Stairs will commence on Tuesday
    - Internal Painting final coat will be completed this week
    - Vinyl Installation will continue for 2 weeks GF & FF
    - External caulking GF & FF will be completed on Thursday
    - GF & FF bathrooms will commence tiling on Tuesday
    - External GF Painting will commence on Friday


    Thanks Jake (Epping)
    Please note - Walls GF & FF will have final coat of paint completed this week if you do damage
    Please let me know (Honesty is the best policy)

    SITE WILL BE CLOSED FROM THE 18th of April & re-open ON THE 28th of April.
    Any issues contact me directly
    Jake
    0437464435

Saha Hava Durumu Tahmini
Geçerli Saha Hava Durumu

Hava Durumu Kullanılamaz


Gözlem kaynağı - Bureau of Meteorology
Gözlem Konumu - Bundoora, VICTORIA
Zaman Dilimi - Doğu Avustralya Standart Saati
Tahmin - Cumartesi, 10 Mayıs

Sunny.
Min: 7C Maks: 24C
Yağmur İhtimali: 5%


Tahmin kaynağı - Bureau of Meteorology
Tahmin Konumu - Watsonia, VICTORIA
Zaman Dilimi - Doğu Avustralya Standart Saati
Yarın - Pazar, 11 Mayıs

Partly cloudy.
Min: 10C Maks: 24C
Yağmur İhtimali: 10%


Önemli Saha Belgeleri
Sahada Yeni misiniz?

Bu sahanın KKD Gereksinimlerini biliyor musunuz?

Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.

Saha KKD Gereksinimlerini Görüntüle

Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.

Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.

Kayda Başla

Sahada Yeni misiniz?

Bu sahanın KKD Gereksinimlerini biliyor musunuz?

Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.

Saha KKD Gereksinimlerini Görüntüle

Sahada Yeni misiniz?

Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.

Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.

Kayda Başla