10th Haziran 2025, Weekly bulletin 10th June (Epping)
Hi all
I hope everyone enjoyed the long weekend.
This week at Epping :
Tuesday, Wednesday, Thursday, Friday
- FF & GF landscape will be continued throughout the week
- Balustrade Glass Install will commence Thursday
- Lift install is scheduled for the whole week
- Stainless steel kitchen install is scheduled for Wednesday
- Carpark Linemarking is scheduled for Wednesday
- Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
- Carpentry fit off will be completed Wednesday
- Power is TBC
- Pre final inspection is scheduled 10am
All outstanding works to be completed prior too
Thanks Jake (Epping)
Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion. -
02nd Haziran 2025, Weekly bulletin Monday 2nd of June
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week
- FF & GF landscape will be continued throughout the week
- Builders clean is scheduled for Monday & Tuesday
- Plumbing fit off will be completed by Wednesday
- Balustrade Glass Install will commence Monday
- Lift install is scheduled for the whole week
- Toilet partitions are scheduled for Tuesday
- Caulking will continue Thursday onwards
- Friday power will be connected to site
Site is closed Monday 9th of June Due to a public holiday.
Thanks Jake (Epping)
Please note - All subcontractors are to clean there own mess as the internal clean will be completed -
26th Mayıs 2025, Weekly bulletin Epping 26th of May
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week
- FF & GF landscape will be continued throughout the week
- Mechanical fit off will start Monday & be completed by Friday
- Plumbing fit off will be completed by Friday
- Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
- Lift delivery is scheduled for the 29th of May
- Site shed & office will be removed on the 30th of May (AM)
Thanks Jake (Epping)
Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.
Geçerli Saha Hava Durumu
Hava Durumu Kullanılamaz
Gözlem Konumu - Bundoora, VICTORIA
Zaman Dilimi - Doğu Avustralya Standart Saati
Tahmin - Cuma, 27 Haziran
Partly cloudy.
Min: 3C Maks: 15C
Yağmur İhtimali: 10%
Tahmin Konumu - Watsonia, VICTORIA
Zaman Dilimi - Doğu Avustralya Standart Saati
Yarın - Cumartesi, 28 Haziran
Partly cloudy.
Min: 4C Maks: 15C
Yağmur İhtimali: 30%
Beklenen Yağmur: 0 kime 1mm
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.