126A Hayston Boulevard, Epping
Seneste bulletiner
  • 05th maj 2025, Weekly bulletin Monday 5th of May (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will start Monday & continue throughout the week.
    - Tiling will commence on Monday for the GF + FF and continue throughout the week.
    - FF landscape will be Monday - Friday
    - Mechanical fit off will continue throughout the week.
    - Plumbing fit off will continue throughout the week

    Thanks Jake (Epping)
    Please note - Walls GF & FF have final coat of paint completed so please be careful.

  • 14th april 2025, Weekly bulletin Monday 14th of April (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday
    - Skirting install GF & FF
    - Scaffolding will be removed in the stairs
    - Vinyl Installation will continue for the week GF & FF
    - External caulking GF & FF will be completed on Monday
    - GF & FF bathrooms will continue tiling on Thursday
    - External Fence work will commence on Tuesday and continue throughout the week
    - Electrical fit off will commence today and continue throughout the week
    - Joinery install will commence today and be completed on Tuesday
    - Brick wash will be commence on Wednesday


    Thanks Jake (Epping)
    Please note - Walls GF & FF will have final coat of paint completed this week if you do damage
    Please let me know (Honesty is the best policy)

    SITE WILL BE CLOSED ON THE 18th of April & re-open ON THE 28th of April.
    Any issues contact me directly
    Jake
    0437464435

  • 07th april 2025, Weekly Bulletin Monday 7th of April (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday & Friday
    - External cladding will continue throughout the week.
    - Plaster Stairs will commence on Tuesday
    - Internal Painting final coat will be completed this week
    - Vinyl Installation will continue for 2 weeks GF & FF
    - External caulking GF & FF will be completed on Thursday
    - GF & FF bathrooms will commence tiling on Tuesday
    - External GF Painting will commence on Friday


    Thanks Jake (Epping)
    Please note - Walls GF & FF will have final coat of paint completed this week if you do damage
    Please let me know (Honesty is the best policy)

    SITE WILL BE CLOSED FROM THE 18th of April & re-open ON THE 28th of April.
    Any issues contact me directly
    Jake
    0437464435

Websted vejrudsigt
Aktuelt vejr på stedet

Weather Not Available


Observation hentet fra - Bureau of Meteorology
Observationssted - Bundoora, VICTORIA
Tidszone - Østaustralsk normaltid
Prognose - lørdag, 10 maj

Sunny.
Min.: 7C Maks.: 24C
Risiko for regn: 5%


Prognosen stammer fra - Bureau of Meteorology
Prognosens placering - Watsonia, VICTORIA
Tidszone - Østaustralsk normaltid
Imorgen - søndag, 11 maj

Partly cloudy.
Min.: 10C Maks.: 24C
Risiko for regn: 10%


Vigtige dokumenter fra webstedet
Ny på stedet?

Kender du kravene for personlige værnemidler til dette sted?

Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.

Se krav til personlig beskyttelsesudstyr på stedet

Kom hurtigere i gang med arbejdet, når du ankommer til stedet.

Afslut din webstedsregistrering online, når det passer dig, og spar tid.

Begynd registrering

Ny på stedet?

Kender du kravene for personlige værnemidler til dette sted?

Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.

Se krav til personlig beskyttelsesudstyr på stedet

Ny på stedet?

Kom hurtigere i gang med arbejdet, når du ankommer til stedet.

Afslut din webstedsregistrering online, når det passer dig, og spar tid.

Begynd registrering