126A Hayston Boulevard, Epping - Öffentlicher Projektstandort
-
10th Juni 2025, Weekly bulletin 10th June (Epping)
Hi all
I hope everyone enjoyed the long weekend.
This week at Epping :
Tuesday, Wednesday, Thursday, Friday
- FF & GF landscape will be continued throughout the week
- Balustrade Glass Install will commence Thursday
- Lift install is scheduled for the whole week
- Stainless steel kitchen install is scheduled for Wednesday
- Carpark Linemarking is scheduled for Wednesday
- Tactile's, Bollards, stair nosings, & wheel stops will be installed on Thursday
- Carpentry fit off will be completed Wednesday
- Power is TBC
- Pre final inspection is scheduled 10am
All outstanding works to be completed prior too
Thanks Jake (Epping)
Please note - All subcontractors are to keep the site in immaculate condition as the job is near completion. -
02nd Juni 2025, Weekly bulletin Monday 2nd of June
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week
- FF & GF landscape will be continued throughout the week
- Builders clean is scheduled for Monday & Tuesday
- Plumbing fit off will be completed by Wednesday
- Balustrade Glass Install will commence Monday
- Lift install is scheduled for the whole week
- Toilet partitions are scheduled for Tuesday
- Caulking will continue Thursday onwards
- Friday power will be connected to site
Site is closed Monday 9th of June Due to a public holiday.
Thanks Jake (Epping)
Please note - All subcontractors are to clean there own mess as the internal clean will be completed -
26th Mai 2025, Weekly bulletin Epping 26th of May
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week
- FF & GF landscape will be continued throughout the week
- Mechanical fit off will start Monday & be completed by Friday
- Plumbing fit off will be completed by Friday
- Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
- Lift delivery is scheduled for the 29th of May
- Site shed & office will be removed on the 30th of May (AM)
Thanks Jake (Epping)
Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.
Aktuelles Wetter am Standort
Wetter nicht verfügbar
Beobachtungsstandort - Bundoora, VICTORIA
Zeitzone - Ostaustralische Normalzeit
Vorhersage - Freitag, 27 Juni
Partly cloudy.
Min.: 3C Max.: 15C
Niederschlagswahrscheinlichkeit: 10%
Prognose Standort - Watsonia, VICTORIA
Zeitzone - Ostaustralische Normalzeit
Morgen - Samstag, 28 Juni
Partly cloudy.
Min.: 4C Max.: 15C
Niederschlagswahrscheinlichkeit: 30%
Erwarteter Niederschlag: 0 bis 1mm
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.