126A Hayston Boulevard, Epping - Public Project Site
-
26th May 2025, Weekly bulletin Epping 26th of May
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week
- FF & GF landscape will be continued throughout the week
- Mechanical fit off will start Monday & be completed by Friday
- Plumbing fit off will be completed by Friday
- Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
- Lift delivery is scheduled for the 29th of May
- Site shed & office will be removed on the 30th of May (AM)
Thanks Jake (Epping)
Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover. -
12th May 2025, Weekly bulletin Monday 12th of May (Epping)
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will continue throughout the week & concrete poured on Thursday
- Tiling will continue throughout the week FF & GF
- FF landscape will be continued throughout the week
- Range-hood installation will commence on Friday
- Plumbing fit off will continue from Wednesday onwards
- Front entry walkway will be commencing Wednesday & poured on Friday
- Balustrade post will be commencing installation later in the week for the upper deck
- Carpentry fit off will continue throughout the week.
Thanks Jake (Epping)
Please note - Walls GF & FF have final coat of paint completed so please be careful. -
05th May 2025, Weekly bulletin Monday 5th of May (Epping)
Hi all
This week at Epping :
Monday, Tuesday, Wednesday, Thursday, Friday
- External Perimeter fencing works will start Monday & continue throughout the week.
- Tiling will commence on Monday for the GF + FF and continue throughout the week.
- FF landscape will be Monday - Friday
- Mechanical fit off will continue throughout the week.
- Plumbing fit off will continue throughout the week
Thanks Jake (Epping)
Please note - Walls GF & FF have final coat of paint completed so please be careful.
Current Site Weather
Weather Not Available
Observation Location - Bundoora, VICTORIA
Time Zone - Australian Eastern Standard Time
Forecast - Saturday, 31 May
Partly cloudy.
Min: 4C Max: 17C
Chance of Rain: 10%
Forecast Location - Watsonia, VICTORIA
Time Zone - Australian Eastern Standard Time
Tomorrow - Sunday, 1 June
Partly cloudy.
Min: 7C Max: 18C
Chance of Rain: 30%
Expected Rainfall: 0 to 1mm
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.