  • 26th May 2025, Weekly bulletin Epping 26th of May

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week
    - FF & GF landscape will be continued throughout the week
    - Mechanical fit off will start Monday & be completed by Friday
    - Plumbing fit off will be completed by Friday
    - Balustrade post will be completed by Tuesday & glass delivery is scheduled for Friday & install the following week
    - Lift delivery is scheduled for the 29th of May
    - Site shed & office will be removed on the 30th of May (AM)

    Thanks Jake (Epping)
    Please note - The building is near completion and everyone must be aware of there surroundings as any damage will cause delays in Handover.

  • 12th May 2025, Weekly bulletin Monday 12th of May (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will continue throughout the week & concrete poured on Thursday
    - Tiling will continue throughout the week FF & GF
    - FF landscape will be continued throughout the week
    - Range-hood installation will commence on Friday
    - Plumbing fit off will continue from Wednesday onwards
    - Front entry walkway will be commencing Wednesday & poured on Friday
    - Balustrade post will be commencing installation later in the week for the upper deck
    - Carpentry fit off will continue throughout the week.

    Thanks Jake (Epping)
    Please note - Walls GF & FF have final coat of paint completed so please be careful.

  • 05th May 2025, Weekly bulletin Monday 5th of May (Epping)

    Hi all

    This week at Epping :

    Monday, Tuesday, Wednesday, Thursday, Friday
    - External Perimeter fencing works will start Monday & continue throughout the week.
    - Tiling will commence on Monday for the GF + FF and continue throughout the week.
    - FF landscape will be Monday - Friday
    - Mechanical fit off will continue throughout the week.
    - Plumbing fit off will continue throughout the week

    Thanks Jake (Epping)
    Please note - Walls GF & FF have final coat of paint completed so please be careful.

Site Weather Forecast
Current Site Weather

Weather Not Available


Observation sourced from - Bureau of Meteorology
Observation Location - Bundoora, VICTORIA
Time Zone - Australian Eastern Standard Time
Forecast - Saturday, 31 May

Partly cloudy.
Min: 4C Max: 17C
Chance of Rain: 10%


Forecast sourced from - Bureau of Meteorology
Forecast Location - Watsonia, VICTORIA
Time Zone - Australian Eastern Standard Time
Tomorrow - Sunday, 1 June

Partly cloudy.
Min: 7C Max: 18C
Chance of Rain: 30%
Expected Rainfall: 0 to 1mm


Important Site Documents
New to Site?

Do you know the PPE Requirements for this site?

Ensure you have the correct safety equipment for your first day at the site.

View Site PPE Requirements

Get started working sooner when you arrive on site.

Complete your site registration online at your convenience and save yourself time.

Begin Registration

New to Site?

Do you know the PPE Requirements for this site?

Ensure you have the correct safety equipment for your first day at the site.

View Site PPE Requirements

New to Site?

Get started working sooner when you arrive on site.

Complete your site registration online at your convenience and save yourself time.

Begin Registration