Senaste bulletiner
  • 02nd mars 2026, 104 Albert street Preston

    Gday everyone,

    2 week look ahead.

    02/03-06/03

    We are looking at fitting off everything inside, vantage, national plumbing and inex are our front runners this week.
    -Thursday, 05/03, we will be removing spoil from site, so please no deliveries.
    -kitchen install on the Friday, 06/03.

    The following week, 10/03-13/03.

    Still looking at finishing fitting off with econium joining us.
    -there will be another day of spoil removal on Thursday, 12/03.

    Monday, 09/03, is a public holiday.

    Regards,
    Damien

  • 16th februari 2026, 104 Albert street preston

    Gday everyone,

    Just a reminder we are starting our major under works at the front of site this Wednesday, 18/02. This means NO PARKING ON SITE for the rest of the week and possibly next week.
    I’d also like to add that the flooring will be finished this week. So please BRING A SPARE PAIR OF SHOES. Any damage to flooring will result in back charges.

    Any queries please don’t hesitate to reach out.

    Regards,
    Damien

  • 05th januari 2026, Welcome back to wheelers hill

    Weekly bulletin.
    Welcome back to Wheelers hill

    Monday 05/01/2026
    ICC Return to site and begin basement SOG prep
     
    Tuesday 06/01/2026
    ICC continue basement SOG prep
     
    Wednesday 07/01/2026
    ICC Poly and Mesh Basement SOG
     
    Thursday 08/01/2026
    ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
    Preslab Inspection in afternoon
     
    Friday 09/01/2026
    ICC Pour Basement Slab
     
    Saturday 10/01/2026
    ICC Sawcut Slab
    ICC Install Starter Bars for Columns
     
    Monday 12/01/2026
    Adbri Block Delivery
    ICC Cages and Formwork for Columns
    Masonry Masters Install Blocks
     
    Tuesday 13/01/2026
    ICC Cages and Formwork for Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Wednesday 14/01/2026
    ICC Close Up Formwork for Columns
    Column Inspection
    ICC Pour Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Thursday 15/01/2026
    Donmar Corefill Blocks
    ICC Ramp Prep
    Ramp Inspection
     
    Friday 16/01/2026
    ICC Pour Ramp

Väderprognos för byggarbetsplatsen
Nuvarande väder på platsen

Senast uppdaterad den: 10:21
Temperatur: 18°C (App 19°C)
Vindhastighet: 4KMH
Max. vind: 9KMH @05:21
Regn sedan klockan 9 på morgonen: 0,0mm
Min temp: 15°C @05:05
Max temp: 26°C @15:19 2026-03-05
Vindstöt: 6KMH
Max Gust: 9KMH @09:21


Observation hämtad från - Bureau of Meteorology
Observationsplats - Essendon Airport, VICTORIA
Tidszon - östaustralisk normaltid
Prognos - fredag, 6 mars

Cloudy.
Min: 16°C Max: 21°C
Risk för regn: 30%
Förväntad nederbörd: 0 till 1mm


Prognos hämtad från - Bureau of Meteorology
Prognosplats - Melbourne, VICTORIA
Tidszon - östaustralisk normaltid
Imorgon - lördag, 7 mars

Cloudy.
Min: 14°C Max: 25°C
Risk för regn: 5%


Viktiga platsdokument
Ny på platsen?

Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?

Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.

Visa platsens krav på personlig skyddsutrustning

Kom igång med arbetet snabbare när du anländer till arbetsplatsen.

Slutför din platsregistrering online när det passar dig och spara tid.

Börja registreringen

Ny på platsen?

Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?

Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.

Visa platsens krav på personlig skyddsutrustning

Ny på platsen?

Kom igång med arbetet snabbare när du anländer till arbetsplatsen.

Slutför din platsregistrering online när det passar dig och spara tid.

Börja registreringen