  • 02nd marts 2026, 104 Albert street Preston

    Gday everyone,

    2 week look ahead.

    02/03-06/03

    We are looking at fitting off everything inside, vantage, national plumbing and inex are our front runners this week.
    -Thursday, 05/03, we will be removing spoil from site, so please no deliveries.
    -kitchen install on the Friday, 06/03.

    The following week, 10/03-13/03.

    Still looking at finishing fitting off with econium joining us.
    -there will be another day of spoil removal on Thursday, 12/03.

    Monday, 09/03, is a public holiday.

    Regards,
    Damien

  • 16th februar 2026, 104 Albert street preston

    Gday everyone,

    Just a reminder we are starting our major under works at the front of site this Wednesday, 18/02. This means NO PARKING ON SITE for the rest of the week and possibly next week.
    I’d also like to add that the flooring will be finished this week. So please BRING A SPARE PAIR OF SHOES. Any damage to flooring will result in back charges.

    Any queries please don’t hesitate to reach out.

    Regards,
    Damien

  • 05th januar 2026, Welcome back to wheelers hill

    Weekly bulletin.
    Welcome back to Wheelers hill

    Monday 05/01/2026
    ICC Return to site and begin basement SOG prep
     
    Tuesday 06/01/2026
    ICC continue basement SOG prep
     
    Wednesday 07/01/2026
    ICC Poly and Mesh Basement SOG
     
    Thursday 08/01/2026
    ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
    Preslab Inspection in afternoon
     
    Friday 09/01/2026
    ICC Pour Basement Slab
     
    Saturday 10/01/2026
    ICC Sawcut Slab
    ICC Install Starter Bars for Columns
     
    Monday 12/01/2026
    Adbri Block Delivery
    ICC Cages and Formwork for Columns
    Masonry Masters Install Blocks
     
    Tuesday 13/01/2026
    ICC Cages and Formwork for Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Wednesday 14/01/2026
    ICC Close Up Formwork for Columns
    Column Inspection
    ICC Pour Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Thursday 15/01/2026
    Donmar Corefill Blocks
    ICC Ramp Prep
    Ramp Inspection
     
    Friday 16/01/2026
    ICC Pour Ramp

Websted vejrudsigt
Aktuelt vejr på stedet

Sidst opdateret kl.: 11:31
Temperatur: 24C (App 24C)
Vindhastighed: 9KMH
Maks. Vind: 11KMH @10:21
Regn siden 9:00: 0,0mm
Min. temp.: 18C @06:11
Maks. temp.: 31C @15:43 09-03-2026
Vindstød: 15KMH
Maks. støv: 15KMH @11:31


Observation hentet fra - Bureau of Meteorology
Observationssted - Essendon Airport, VICTORIA
Tidszone - Østaustralsk normaltid
Prognose - tirsdag, 10 marts

Sunny.
Min.: 19C Maks.: 34C
Risiko for regn: 30%
Forventet nedbør: 0 til 1mm


Prognosen stammer fra - Bureau of Meteorology
Prognosens placering - Melbourne, VICTORIA
Tidszone - Østaustralsk normaltid
Imorgen - onsdag, 11 marts

Shower or two.
Min.: 15C Maks.: 19C
Risiko for regn: 60%
Forventet nedbør: 0 til 2mm


Vigtige dokumenter fra webstedet
Ny på stedet?

Kender du kravene for personlige værnemidler til dette sted?

Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.

Se krav til personlig beskyttelsesudstyr på stedet

Kom hurtigere i gang med arbejdet, når du ankommer til stedet.

Afslut din webstedsregistrering online, når det passer dig, og spar tid.

Begynd registrering

Ny på stedet?

Kender du kravene for personlige værnemidler til dette sted?

Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.

Se krav til personlig beskyttelsesudstyr på stedet

Ny på stedet?

Kom hurtigere i gang med arbejdet, når du ankommer til stedet.

Afslut din webstedsregistrering online, når det passer dig, og spar tid.

Begynd registrering