104-106 Albert Street, Preston - Cantiere del progetto pubblico
-
02nd marzo 2026, 104 Albert street Preston
Gday everyone,
2 week look ahead.
02/03-06/03
We are looking at fitting off everything inside, vantage, national plumbing and inex are our front runners this week.
-Thursday, 05/03, we will be removing spoil from site, so please no deliveries.
-kitchen install on the Friday, 06/03.
The following week, 10/03-13/03.
Still looking at finishing fitting off with econium joining us.
-there will be another day of spoil removal on Thursday, 12/03.
Monday, 09/03, is a public holiday.
Regards,
Damien -
16th febbraio 2026, 104 Albert street preston
Gday everyone,
Just a reminder we are starting our major under works at the front of site this Wednesday, 18/02. This means NO PARKING ON SITE for the rest of the week and possibly next week.
I’d also like to add that the flooring will be finished this week. So please BRING A SPARE PAIR OF SHOES. Any damage to flooring will result in back charges.
Any queries please don’t hesitate to reach out.
Regards,
Damien
-
05th gennaio 2026, Welcome back to wheelers hill
Weekly bulletin.
Welcome back to Wheelers hill
Monday 05/01/2026
ICC Return to site and begin basement SOG prep
Tuesday 06/01/2026
ICC continue basement SOG prep
Wednesday 07/01/2026
ICC Poly and Mesh Basement SOG
Thursday 08/01/2026
ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
Preslab Inspection in afternoon
Friday 09/01/2026
ICC Pour Basement Slab
Saturday 10/01/2026
ICC Sawcut Slab
ICC Install Starter Bars for Columns
Monday 12/01/2026
Adbri Block Delivery
ICC Cages and Formwork for Columns
Masonry Masters Install Blocks
Tuesday 13/01/2026
ICC Cages and Formwork for Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Wednesday 14/01/2026
ICC Close Up Formwork for Columns
Column Inspection
ICC Pour Columns
ICC Ramp Slab Prep
Masonry Masters Install Blocks
Thursday 15/01/2026
Donmar Corefill Blocks
ICC Ramp Prep
Ramp Inspection
Friday 16/01/2026
ICC Pour Ramp
Meteo attuale del cantiere
Ultimo aggiornamento su: 13:21
Temperatura: 28C (App 28C)
Velocità del vento: 13KMH
Max. Vento: 13KMH @13:21
Pioggia dalle 9.00: 0,0mm
Temp min: 18C @06:11
Temp max: 31C @15:43 09/03/2026
Raffica: 15KMH
Raffiche max: 15KMH @13:21
Luogo di osservazione - Essendon Airport, VICTORIA
Fuso orario - Ora standard dell’Australia orientale
Previsioni - martedì, 10 marzo
Sunny.
Min: 19C Max: 34C
Possibilità di pioggia: 30%
Precipitazioni previste: 0 a 1mm
Luogo previsioni - Melbourne, VICTORIA
Fuso orario - Ora standard dell’Australia orientale
Domani - mercoledì, 11 marzo
Shower or two.
Min: 15C Max: 19C
Possibilità di pioggia: 60%
Precipitazioni previste: 0 a 2mm
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.