104-106 Albert Street, Preston
Últimos Boletines
  • 02nd marzo 2026, 104 Albert street Preston

    Gday everyone,

    2 week look ahead.

    02/03-06/03

    We are looking at fitting off everything inside, vantage, national plumbing and inex are our front runners this week.
    -Thursday, 05/03, we will be removing spoil from site, so please no deliveries.
    -kitchen install on the Friday, 06/03.

    The following week, 10/03-13/03.

    Still looking at finishing fitting off with econium joining us.
    -there will be another day of spoil removal on Thursday, 12/03.

    Monday, 09/03, is a public holiday.

    Regards,
    Damien

  • 16th febrero 2026, 104 Albert street preston

    Gday everyone,

    Just a reminder we are starting our major under works at the front of site this Wednesday, 18/02. This means NO PARKING ON SITE for the rest of the week and possibly next week.
    I’d also like to add that the flooring will be finished this week. So please BRING A SPARE PAIR OF SHOES. Any damage to flooring will result in back charges.

    Any queries please don’t hesitate to reach out.

    Regards,
    Damien

  • 05th enero 2026, Welcome back to wheelers hill

    Weekly bulletin.
    Welcome back to Wheelers hill

    Monday 05/01/2026
    ICC Return to site and begin basement SOG prep
     
    Tuesday 06/01/2026
    ICC continue basement SOG prep
     
    Wednesday 07/01/2026
    ICC Poly and Mesh Basement SOG
     
    Thursday 08/01/2026
    ICC Continues Poly and Mesh, Set Evaporation Drains, Set Basement Pit Lid Heights
    Preslab Inspection in afternoon
     
    Friday 09/01/2026
    ICC Pour Basement Slab
     
    Saturday 10/01/2026
    ICC Sawcut Slab
    ICC Install Starter Bars for Columns
     
    Monday 12/01/2026
    Adbri Block Delivery
    ICC Cages and Formwork for Columns
    Masonry Masters Install Blocks
     
    Tuesday 13/01/2026
    ICC Cages and Formwork for Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Wednesday 14/01/2026
    ICC Close Up Formwork for Columns
    Column Inspection
    ICC Pour Columns
    ICC Ramp Slab Prep
    Masonry Masters Install Blocks
     
    Thursday 15/01/2026
    Donmar Corefill Blocks
    ICC Ramp Prep
    Ramp Inspection
     
    Friday 16/01/2026
    ICC Pour Ramp

Pronóstico del tiempo para la Obra
Tiempo en Obra actual

Última actualización el: 11:31 AM
Temperatura: 24C (Aplicación 24C)
Velocidad del viento: 9MPH
Máx. Viento: 11MPH @10:21 AM
Lluvia desde las 9 a.m.: 0.0mm
Temp mín: 18C @6:11 AM
Temp máx: 31C @3:43 PM 3/9/2026
Ráfaga: 15MPH
Ráfagas máx: 15MPH @11:31 AM


Observación obtenida de - Bureau of Meteorology
Lugar de observación - Essendon Airport, VICTORIA
Zona horaria - hora estándar de Australia oriental
Pronóstico - martes, 10 marzo

Sunny.
Mín: 19C Máx: 34C
Probabilidad de lluvia: 30%
Se esperan precipitaciones: 0 para 1mm


Pronóstico obtenido de - Bureau of Meteorology
Lugar de la previsión - Melbourne, VICTORIA
Zona horaria - hora estándar de Australia oriental
Mañana - miércoles, 11 marzo

Shower or two.
Mín: 15C Máx: 19C
Probabilidad de lluvia: 60%
Se esperan precipitaciones: 0 para 2mm


Documentos importantes de la Obra
¿Primera vez en la Obra?

¿Conoce los requisitos de PPE para esta Obra?

Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.

Ver los requisitos de PPE para la Obra

Empiece a trabajar en cuanto llegue a la obra.

Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.

Comenzar registro

¿Primera vez en la Obra?

¿Conoce los requisitos de PPE para esta Obra?

Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.

Ver los requisitos de PPE para la Obra

¿Primera vez en la Obra?

Empiece a trabajar en cuanto llegue a la obra.

Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.

Comenzar registro