  • 14th dubna 2025, Weekly bulletin

    Good afternoon all,

    The following will be taking place out at clayton south.

    - Electrical fit-off will continue Monday & Tuesday.
    - Mechanical fit-off will start Monday & continue through until Thursday.
    - Plumbing fit-off will start Monday & continue through until Thursday.
    - Vinyl planks will be installed on GF from Tuesday.
    Landscaping will commence on GF from Wednesday.

    Please help ensure the site is kept tidy and all rubbish goes into the bins provided.
    All members are reminded that they need to sign-in each and every day.

    Thanks,
    Brendan

  • 24th února 2025, Weekly bulletin.

    Good afternoon all,

    The following will be taking place out at Clayton south.

    - Works will begin on the concrete driveway at the rear of the property with a concrete pour taking place on Friday so please be aware of machines & vehicles.
    - Plasterers will be continuing work on GF & finishing up towards the end of the week.
    - Cladding carpenters will continue with the soffit & cladding install.
    - Temporary handrail will be coming down this week as the glass is being installed.
    - Lower roof frames will be getting sheeted on Monday.


    Please help ensure the site is kept tidy and all rubbish goes into the bins provided.
    All members are reminded that they need to sign-in each and every day.

    Thanks,
    Brendan

  • 17th února 2025, Weekly Bulletin.

    Good morning all,

    The following will be taking place out at Clayton south.

    - Painters will be preparing & painting exterior of level one.
    - Plasterers will be continuing work on GF.
    - Cladding carpenters will continue with the soffit & cladding install.
    - Window glazing will be finished.
    - Lower roof frames will be installed.

    Please help ensure the site is kept tidy and all rubbish goes into the bins provided.
    All members are reminded that they need to sign-in each and every day.

    Thanks,
    Brendan

Předpověď počasí pro stavbu
Aktuální počasí na pracovišti

Nedostupné


Pozorování vycházející z - Nedostupné
Časové pásmo - východoaustralský standardní čas
Předpověď – sobota, 10 května

Sunny.
Min: 7C Max: 24C
Možnost deště: 5%


Předpověď pochází z – Bureau of Meteorology
Místo předpovědi – Moorabbin, VICTORIA
Časové pásmo - východoaustralský standardní čas
Zítra - neděle, 11 května

Partly cloudy.
Min: 11C Max: 23C
Možnost deště: 10%


Důležité dokumenty pracoviště
Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci

Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Novinka na pracovišti?

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci